CALIM Consultancy Services
Back to Insights
Claims DefenceEditorial

Why 80% of LD Claims Originate in Administration, Not Drafting

1 min read
Why 80% of LD Claims Originate in Administration, Not Drafting

The most expensive contract failures are not born in the legal review. They are born in the daily administration - missed notices, expired time bars, and undocumented variations.

Key takeaways

  • Roughly 80% of LD claims that succeed against contractors come from poor administration, not poor drafting - the protections existed but were never activated.
  • A delay event is often acknowledged informally, nobody issues a formal notice, and the 28-day window passes before anyone checks the actual deadline.
  • A verbally instructed variation with no completed valuation and agreement leaves no documented basis to argue the completion date should have been extended.
  • These administration gaps are standard operating reality on GCC construction projects, and they are entirely preventable with proper contract administration discipline.

When a liquidated damages claim lands on a contractor's desk, the instinct is to look at the contract drafting:

  • Was the LD rate reasonable?
  • Was the cap adequate?
  • Were the conditions precedent properly defined?

These are valid questions, but they rarely address the actual cause of the exposure.

In CALIM's experience across dozens of engagements, approximately 80% of LD claims that succeed against contractors do so not because of poor drafting, but because of poor administration. The contract was adequate. The protections were there. But the day-to-day discipline required to activate those protections was absent.

The pattern repeats: a delay event occurs. The project team acknowledges it informally. Nobody issues a formal notice under the contract. The 28-day window passes before anyone checks when the notice deadline actually falls. The entitlement to an extension of time - which would have reduced or eliminated the LD exposure - is lost.

Or a variation is instructed verbally. The work is done. The cost is incurred. But the formal process of instruction, valuation, and agreement is never completed. When the employer assesses LDs against the original completion date, the contractor has no documented basis to argue that the completion date should have been extended.

These are not exotic scenarios. They are the standard operating reality on most construction projects in the GCC. And they are entirely preventable with proper contract administration discipline.

CC

CALIM Contracts Desk

Contracts, Claims & Commercial Advisory

Reviewed for accuracy by CALIM's senior leadership: Dr. Varghese Koshy Panicker (Founder & CEO), Adv. Jayakumar Madapattu (Co-Founder & CLO), Tins Varghese (Co-Founder & CCSO).

This article is general information about construction contract practice, not legal advice. Entitlement, notice requirements and time bars turn on the specific wording of your contract and the governing law, which vary between projects and jurisdictions. Obtain advice tailored to your contract before acting on anything set out here.

Get Started

Have a question our articles do not answer?

The fastest answer is usually a 30-minute call with one of our senior specialists.

What kind of dispute or exposure are you facing?

Select one to help us match you with the right specialist.