FIDIC price adjustment calculator. See what the indices are worth.
Enter the valuation, the fixed coefficient a and up to six cost elements with their base and current indices. The calculator checks the coefficients total 1.000, runs the escalation formula and shows the multiplier Pn, the adjusted amount and what each element contributed.
The formula, Sub-Clause 13.8 (1999)
Pn = a + b(Ln/Lo) + c(En/Eo) + d(Mn/Mo) + ...
- a
- Fixed coefficient. Never indexed.
- b, c, d
- Weightings from the table of adjustment data.
- Lo, Eo, Mo
- Base indices at the Base Date.
- Ln, En, Mn
- Current indices, 49 days before the period ends.
The coefficients must total exactly 1.000. A Pn of 1.0386 adds 3.86 percent to the valuation. A Pn below 1 takes money off it.
Price Adjustment Calculator
Figures come from your table of adjustment data and the published indices.
This period's value of work only, not the cumulative Statement total. Leave out work valued at Cost or current prices.= QAR 4,850,000
The part never indexed.
Indexed cost elements
5 of 6Coefficients as decimals, so 30 percent is 0.30. Base index at the Base Date, current index for this period, from the same series.
Live result: Pn 1.038639, +QAR 187,401 see breakdown
Index dates (optional)
Applies the FIDIC 1999 Red and Yellow Book timing. Check your own table or schedule, because amended and 2017 contracts can set different dates.
Including any EOT.
Arithmetic on the inputs you enter, not legal advice. Whether an adjustment is due, and on which indices, turns on your executed contract and the governing law. The example figures are illustrative, not a published index series.
Pn 1.038639. Adjustment +QAR 187,401. Adjusted amount QAR 5,037,401.
Adjustment multiplier Pn
1.038639The indices have risen since the Base Date, so the valuation is adjusted upwards for this period.
Valuation
QAR 4,850,000
Before adjustment.
Adjusted amount
QAR 5,037,401
Valuation multiplied by Pn.
Fixed portion
QAR 727,500
a = 0.150, never indexed.
Indexed portion
QAR 4,122,500
Moves with the indices.
Contribution by cost element
- Labour+QAR 46,560
Index +3.20% since the Base Date, weighted at 0.300
- Reinforcing steel+QAR 66,248
Index +9.11% since the Base Date, weighted at 0.150Largest driver
- Cement and concrete+QAR 20,376
Index +2.80% since the Base Date, weighted at 0.150
- Fuel and energy+QAR 43,518
Index +8.97% since the Base Date, weighted at 0.100
- Plant and equipment+QAR 10,699
Index +1.47% since the Base Date, weighted at 0.150
Which index readings to use
- Base indices (Base Date)
- 16 Feb 2025
- Current indices (49 days before period end)
- 12 Aug 2026
The working, line by line
Each term is coefficient multiplied by current index over base index. The terms add up to Pn. Pn is carried at full precision throughout. If your table or Particular Conditions round the ratios or Pn (for example to 3 or 4 decimals), certified figures will differ slightly.
| Element | Coefficient | Base index | Current index | Current / base | Term in Pn | Contribution |
|---|---|---|---|---|---|---|
| a (fixed, not indexed) | 0.150 | n/a | n/a | n/a | 0.150000 | QAR 0 |
| b Labour | 0.300 | 100 | 103.2 | 1.032000 | 0.309600 | +QAR 46,560 |
| c Reinforcing steel | 0.150 | 118.6 | 129.4 | 1.091062 | 0.163659 | +QAR 66,248 |
| d Cement and concrete | 0.150 | 96.4 | 99.1 | 1.028008 | 0.154201 | +QAR 20,376 |
| e Fuel and energy | 0.100 | 84.7 | 92.3 | 1.089728 | 0.108973 | +QAR 43,518 |
| f Plant and equipment | 0.150 | 102 | 103.5 | 1.014706 | 0.152206 | +QAR 10,699 |
| Total | 1.000 | Pn = 1.038639 | +QAR 187,401 |
How It Works
How the FIDIC price adjustment formula works
The FIDIC price adjustment formula converts movements in published cost indices into a change in what you are paid each month. The value of the work in the period is multiplied by Pn. Pn is built from a fixed coefficient a plus a weighted ratio of current to base index for every cost element. A Pn of 1.0386 adds 3.86 percent to that valuation.
Sub-Clause 13.8 in 1999, Sub-Clause 13.7 in 2017
In the 1999 Red and Yellow Books the mechanism is Sub-Clause 13.8, Adjustments for Changes in Cost, and the formula is written into the General Conditions. The 1999 Silver Book offers it only through the Particular Conditions. The 2017 Red, Yellow and Silver Books moved it to Sub-Clause 13.7 under the same title and took the formula out of the General Conditions altogether. In 2017 the adjustment is whatever the Schedule(s) of cost indexation produce, so the formula itself lives in that schedule, though Sub-Clause 13.7 still carries the surrounding rules: one Schedule per payment currency, no adjustment to work valued at Cost or current prices, the provisional index, and the late-completion freeze.
Where the coefficients come from
Under the 1999 books the coefficients and index sources sit in the table of adjustment data in the Appendix to Tender. FIDIC's guidance describes the usual split. The employer names the cost elements, and the contractor completes the table with an index for each and a coefficient that approximates its share of the cost of the Works. Coefficient a is the non-adjustable portion that never moves. Together, a and the element coefficients must total exactly 1.000, which is why the calculator above will not run until they do.
Tender teams often treat this table as paperwork. It is a pricing decision. The coefficients you submit decide how much of a future cost rise you will ever see again. The 1999 wording lets them be revisited only where Variations have made them unreasonable, unbalanced or inapplicable.
Base date indices and the 49-day lag
The base indices (Lo, Eo, Mo) are the values on the Base Date, which the 1999 books define as 28 days before the latest date for submission of the Tender. The current indices (Ln, En, Mn) are the values on the date 49 days before the last day of the valuation period, because indices are published in arrears. Until the right figure is out, the 1999 wording has the Engineer determine a provisional index for the interim certificate, and the adjustment is recalculated once the real index is available. The optional date fields above apply both offsets for you.
Finishing late has a price here too. If the Works are not complete within the Time for Completion, later adjustments use one of two readings. It is either the index from 49 days before the Time for Completion expired or the current index, whichever is more favourable to the Employer. In a rising market that freezes your indexation at the lower figure, so an extension of time protects your indexation as well as your delay damages position.
No adjustment data, no adjustment
If the contract has no table of adjustment data or Schedule of cost indexation, the Sub-Clause does not apply and gives no adjustment for changes in cost. That is pacta sunt servanda at work: agreements must be kept, and the price is part of the agreement. FIDIC's own 2023 guidance on inflation is plain about it. If the Employer does not take the inflation risk, the Contractor bears it.
Even where the Sub-Clause applies, both editions deem the Accepted Contract Amount to include a contingency for any rise or fall in costs the formula does not fully cover. An index can be accurate and still miss your real cost increase. Not a flaw in the arithmetic. A risk you priced, knowingly or not. Some governing laws, including the civil codes of Qatar and the UAE, contain a hardship provision for exceptional and unforeseeable events that make performance excessively onerous. The threshold is high, and ordinary inflation rarely meets it.
Where the adjustment goes wrong
The errors that cost money are rarely conceptual. They are administrative. A base index is read on the wrong date. A publisher rebases its index series and nobody notices. A provisional index is never recalculated. Work valued at Cost or current prices, which the 1999 wording excludes from adjustment, is swept into the figure anyway. Each error repeats on every certificate until someone checks.
In the 1999 Red Book the adjustment is its own line in the monthly Statement under Sub-Clause 14.3, so it rides on the cycle explained in interim payment certificates. Whether you get indexation at all is settled when the pricing model is chosen, the trade-off set out in fixed price vs remeasurement vs cost-reimbursable. On lump sum work it will not rescue a variation priced at the wrong rate, which is the subject of variations on lump-sum and LSTK contracts.
At CALIM, we check price adjustment line by line against the table, the published indices and the certificates as part of our commercial management for SME contractors.
The formula is simple. Applying it correctly every month is where the money is.
Before You Rely On It
Three things to check behind the number.
The table
- Coefficient a plus the weightings total exactly 1.000
- Each element names its index source
- Weightings move only where Variations unbalance them
The indices
- Base readings taken at the Base Date
- Current readings 49 days before the period ends
- Provisional indices recalculated once published
The contract model
- No table or schedule means no adjustment
- Inflation the formula misses stays with the contractor
- The risk is chosen at tender, not on site
Questions Contractors Ask
Price adjustment, answered.
How do you calculate price adjustment under a FIDIC contract?
Multiply the value of the work in the period by the adjustment multiplier Pn, where Pn = a + b(Ln/Lo) + c(En/Eo) + d(Mn/Mo) and so on for each cost element. Coefficient a is the fixed part, and b, c and d are the weightings in the table of adjustment data. Under the 1999 wording the current indices are read 49 days before the last day of the period and the base indices at the Base Date. The adjustment is the value multiplied by (Pn minus 1), so a Pn of 1.04 adds 4 percent.
What is the fixed coefficient a in the price adjustment formula?
It is the share of each payment that is never indexed. The 1999 FIDIC books describe it as the non-adjustable portion in contractual payments, and it is stated in the table of adjustment data alongside the element coefficients. Because a and the element coefficients together represent the whole payment, they must add up to exactly 1.000. A higher a means less of the price moves with the market, which protects the employer when costs rise and the contractor when they fall.
Is FIDIC Sub-Clause 13.8 the same as Sub-Clause 13.7 in the 2017 edition?
They do the same job under the same title, Adjustments for Changes in Cost. In the 1999 Red and Yellow Books it is Sub-Clause 13.8, with the formula in the General Conditions and the coefficients in the table of adjustment data in the Appendix to Tender. In the 2017 Red, Yellow and Silver Books it is Sub-Clause 13.7, and the method sits in the Schedule(s) of cost indexation. In both, if no table or schedule is included, the Sub-Clause does not apply. The 1999 Silver Book offers it only through the Particular Conditions. Do not confuse either with Sub-Clause 13.7 in the 1999 books, which is Adjustments for Changes in Legislation (13.6 Changes in Laws in 2017), a different clause entirely.
Is a fixed price construction contract adjusted for inflation?
Generally not, unless the contract says so. Where a FIDIC contract has no table of adjustment data or Schedule of cost indexation, the price adjustment Sub-Clause does not apply and the contractor carries the inflation risk inside the price it agreed. That is pacta sunt servanda at work. Relief then depends on other routes, such as a change in law clause or a hardship doctrine in the governing law, and those thresholds are high. Ordinary market inflation rarely meets them, so the decision is really made at tender.
What happens to price adjustment after the Time for Completion has passed?
Under the 1999 FIDIC Red and Yellow Book wording, if the contractor fails to complete within the Time for Completion, later adjustments use either the index applicable 49 days before the Time for Completion expired or the current index, whichever is more favourable to the employer. In a rising market that freezes your indexation at the earlier, lower reading. An extension of time moves the Time for Completion, so a properly secured EOT protects your indexation as well as your exposure to delay damages.
This calculator applies the arithmetic of a FIDIC price adjustment formula to the figures you enter. It is general information, not legal advice, and no consultant-client relationship arises from its use. Whether an adjustment is due, and on which indices, depends on your executed contract, the completed table of adjustment data or Schedule of cost indexation, the indices actually published and the governing law. Take professional advice before relying on any figure.
Get Started
Indexation is arithmetic. Recovering it is administration.
One conversation is usually enough to see whether your price adjustment is being certified correctly, or quietly drifting on every certificate.
What is your notice situation right now?
Select one to help us match you with the right specialist.
