CALIM Consultancy Services
All guidesTopic Guide

Delay, EOT and Prolongation Claims

Delay is where contractors lose the most money they were entitled to keep. An extension of time protects you from liquidated damages; a prolongation claim protects your margin - and they are decided by different tests. This guide brings together CALIM's insights on extension of time, prolongation cost, concurrent delay, disruption, delay analysis methodology, and the contemporaneous records that decide whether a claim survives scrutiny.

Work through the articles below to build a complete picture of how time and money entitlements arise, how they are proven, and where most claims quietly fail on procedure rather than merit.

In this guide

Delay Analysis

Collapsed As-Built Analysis: When But-For Persuades and When It Fails

9 min read
Delay Analysis

Time Impact Analysis vs Windows Analysis: Prospective or Retrospective?

9 min read
Delay Analysis

Windows Analysis and Time Slice: How the Contemporaneous Delay Method Works

10 min read
EOT Claims

Managing EOT Claims on GCC Projects: From Delay Event to Determination

5 min read
Claims Defence

Contemporaneous Records: Meaning, Types and What Tribunals Accept

10 min read
Claims Defence

What Goes in a FIDIC Fully Detailed Claim: The 84-Day Submission Under Clause 20.2.4

8 min read
Delay Analysis

Disruption vs Delay: Claiming for Lost Productivity

8 min read
Delay Analysis

Which Preliminaries and Time-Related Overheads Can You Recover?

8 min read
Delay Analysis

How to Calculate Prolongation Costs: Hudson, Emden and the Actual-Cost Approach

11 min read
Delay Analysis

Concurrent Delay: How It Affects Your Time and Money Entitlement

8 min read
Delay Analysis

Delay Analysis Methods Explained: Time Impact vs As-Planned vs As-Built

10 min read
EOT Claims

What Is a Prolongation Claim - and What Actually Qualifies?

9 min read
Delay Analysis

Excusable, Compensable, Non-Excusable: A Contractor's Map of Delay Types

8 min read
EOT Claims

EOT vs Prolongation: Why They're Not the Same Claim (and Why It Matters to Your Cash)

8 min read
Claims Defence

Claims Consultant vs Lawyer: Who Do You Need, and When?

6 min read
Claims Defence

Why 80% of LD Claims Originate in Administration, Not Drafting

1 min read
Claims Defence

The 28-Day Rule That Kills More Claims Than Any Dispute

1 min read
EOT Claims

Why Do So Many EOT Claims Get Rejected?

2 min read

Ready to act on this?

Explore CALIM's delay analysis and claims support

Learn more

Frequently asked questions

What is the difference between an extension of time and a prolongation claim?

An extension of time (EOT) adjusts the completion date and protects the contractor from liquidated damages for a delay that was the employer's risk. A prolongation claim recovers the additional time-related cost of being on site longer. They are separate entitlements decided by separate tests, which is why a contractor can win the time but still fail to recover the money if the cost claim is not made and substantiated.

Why do so many valid delay claims get rejected?

Most rejected delay claims fail on procedure, not substance. The delay was real and the cost was incurred, but the notice was late, the cause-and-effect link was not demonstrated with contemporaneous records, or the wrong delay analysis method was applied to the available programme evidence. Disciplined notices and record-keeping from day one are what turn a legitimate delay into a recoverable entitlement.

How do I prove a construction delay claim?

A defensible delay claim needs a properly updated programme showing the critical path, timely notices of each delay event, and cause-specific contemporaneous records that let an analyst link the event to the critical delay. The choice of delay analysis method must fit the quality of the records. Reconstructed programmes carry far less evidential weight than contemporaneous ones, so the strength of a claim is largely fixed by the records kept while the work was live.

Get Started

Facing a delay & EOT issue right now?

The fastest answer is usually a 30-minute call with one of our senior specialists.

Which topic matters most to your business right now?

Select one to help us match you with the right specialist.