Late payment interest calculator for FIDIC 14.8 financing charges.
Enter the amount unpaid, the date for payment and the date the money arrived. See the financing charges your contract adds, compounded monthly, with a schedule you can put straight into your next Statement.
The FIDIC default
At 7.5% a year, a QAR 3.75 million certificate paid late earns QAR 23,437.50 in its first month, and the next month charges on that too.
Financing charges need no notice. Suspension needs 21 days' notice first, and on the unamended forms the termination right opens once a certified amount is more than 42 days late.
Financing charges calculator
The amount, the two dates and the rate. The example below is pre-filled so you can see how it works.
= QAR 3,750,000.00. The certified amount that was not paid on time.
For an interim certificate this is usually 56 days after the Engineer received your Statement, even if the certificate itself issued late.
Still unpaid? Leave today's date.
The 1999 default is the central bank discount rate for the currency of payment plus 3 points. The text gives no fallback where no discount rate is published. The 4.5% shown is an example only.
Arithmetic on the inputs you enter, not legal advice. Entitlement turns on your executed contract, any amendment to Sub-Clause 14.8, and the governing law.
Financing charges QAR 77,120.78. Total due QAR 3,827,120.78. 100 days late.
Financing charges | more than 42 days late
Total now due QAR 3,827,120.78. Another month unpaid adds QAR 23,919.50. On the unamended forms, a certified amount still unpaid 42 days after the time for payment is a trigger for the Contractor's termination right under Sub-Clause 16.2 (16.2.1 in 2017), exercised by notice. It is a serious step with strict formalities, and Particular Conditions often change it. Read how suspension and notice rights work before you serve anything.
Days late
100d
3 full months + 8 days.
Annual rate
7.5%
7.76% effective once compounded.
Total due
QAR 3,827,120.78
Amount unpaid plus financing charges.
Next month adds
QAR 23,919.50
If payment slips one more full month.
Month-by-month schedule
0.625% a monthEach row is one compounding period. The charge is added to the balance before the next month begins.
| From | To | Days | Opening (QAR) | Charge (QAR) | Cumulative (QAR) |
|---|---|---|---|---|---|
| 29 Jun 2026 | 29 Jul 2026 | 30 | 3,750,000.00 | 23,437.50 | 23,437.50 |
| 29 Jul 2026 | 29 Aug 2026 | 31 | 3,773,437.50 | 23,583.98 | 47,021.48 |
| 29 Aug 2026 | 29 Sep 2026 | 31 | 3,797,021.48 | 23,731.38 | 70,752.86 |
| 29 Sep 2026 | 7 Oct 2026 (part) | 8 | 3,820,752.86 | 6,367.92 | 77,120.78 |
| Total | 100 | 77,120.78 | 77,120.78 | ||
Each month after the date for payment is one compounding period at one twelfth of the annual rate, and a final part month is pro-rated by days. FIDIC does not fix a day-count convention, so state your method when you submit the figure. General guidance only, not legal advice. For help pricing and chasing late certificates, see commercial management for SME contractors.
How It Works
How FIDIC financing charges work on a late payment
When an employer pays a certified amount late, FIDIC Sub-Clause 14.8 entitles the contractor to financing charges on the unpaid sum. They compound monthly from the date payment was due until the day it arrives. No claim notice is needed, and no certificate either. The problem is rarely entitlement. It is that nobody puts the number in front of the employer.
What Sub-Clause 14.8 [Delayed Payment] says in the 1999 and 2017 editions
The 1999 Red, Yellow and Silver Books charge three percentage points above the discount rate of the central bank in the country of the currency of payment. The Particular Conditions can substitute another rate. The contractor is entitled to the charges without formal notice or certification, and without prejudice to any other right or remedy. The text gives no fallback where that central bank publishes no discount rate, which is a gap worth closing at tender.
The 2017 edition keeps the three-point margin and the monthly compounding but changes the base rate. It becomes the average bank short-term lending rate to prime borrowers for the currency of payment at the place for payment. Failing that, it is the same rate in the country of that currency, and then the rate fixed by that country's law. It also makes clear that the Sub-Clause 20.2 claims procedure does not apply, so no 28-day notice is needed to keep the charges alive.
| Sub-Clause 14.8 | FIDIC 1999 | FIDIC 2017 |
|---|---|---|
| Base rate | Discount rate of the central bank in the country of the currency of payment | Average bank short-term lending rate to prime borrowers for the currency of payment at the place for payment |
| Margin | 3 percentage points | 3 percentage points |
| If no base rate exists | No fallback stated | Same rate in the currency's country, then the rate fixed by its law |
| Compounding | Monthly | Monthly |
| Notice or certificate | Not required | Not required, and no Sub-Clause 20.2 claim |
| Clock starts | Date for payment under 14.7 | Date for payment under 14.7 |
| Another rate stated in | Particular Conditions | Contract Data |
When the clock starts
The period of delay is deemed to start on the date for payment under Sub-Clause 14.7, irrespective of when the interim certificate is actually issued. For an interim certificate that date is 56 days after the Engineer receives the Statement and supporting documents, unless the contract sets another period. A late certificate does not move the start date, so every day the employer's approval process absorbs is a day on the meter. Our guide to interim payment certificates walks through the valuation cycle behind those dates.
Sub-Clause 14.8 bites on payment, not on valuation. If the Engineer certified less than your Statement claimed, the gap is a separate argument. The steps are set out in what to do when an interim payment is certified short.
How the calculator compounds
FIDIC says the charges are compounded monthly but does not fix a day-count convention. The calculator treats each month after the date for payment as one period at one twelfth of the annual rate. Each charge joins the balance, and a final part month is pro-rated by days. On QAR 3.75 million at 7.5% a year, the first month adds QAR 23,437.50. The second adds QAR 23,583.98, because it also charges on the first month's charge. If the reference rate changed during a long delay, run the first stretch up to the date the rate changed, then enter its total due as the amount unpaid for the next stretch, starting on that date, at the new rate, so the earlier charges keep compounding instead of being dropped. The calculator assumes a single sum paid in full on one date. For several unpaid certificates or a part payment, run each unpaid tranche separately from its own date for payment.
Financing charges, suspension and termination
Financing charges compensate the delay. They do not end it. Under the unamended Sub-Clause 16.1, the contractor may suspend work or reduce the rate of work after giving not less than 21 days' notice. The suspension does not prejudice the financing charges. If a certified amount is still unpaid 42 days after the time for payment expires, Sub-Clause 16.2 (16.2.1 in 2017) opens a right to terminate by notice. Both are heavy instruments with strict formalities, and a defective notice can make the contractor the party in breach. The guide to remedies for non-payment by a main contractor covers the same suspension and notice discipline one tier down the supply chain.
If your contract uses FIDIC's 2022 reprint of the 2017 Red, Yellow or Silver Book, a further lever applies. New Sub-Clause 21.4 deems a Dispute to have arisen where financing charges remain unpaid 28 days after the contractor requests them, referable to the DAAB without a Notice of Dissatisfaction.
When the Particular Conditions change the answer
Everything above assumes the General Conditions survived negotiation. In the GCC and many other markets they often do not. Employer-drafted Particular Conditions regularly reduce the margin, substitute a fixed rate, cap the charges or delete Sub-Clause 14.8 altogether. The governing law matters too, because some legal systems restrict charges that resemble interest. A clause can be standard FIDIC and still be absent from your contract. Read the executed Particular Conditions first, then use the custom rate option to model what they actually say.
In CALIM's experience across dozens of engagements, the contractors who recover financing charges are the ones who price them in every Statement, not at final account. At CALIM, we track certified sums against their payment dates through our commercial management service for SME contractors, so late money is priced on the day it becomes late.
Late payment is only free when nobody does the arithmetic.
The Remedies
Three things late payment unlocks.
Financing charges
- Run from the date for payment, not the certificate date
- No formal notice or certification needed
- Compounded monthly at the contract rate
- Put a calculation into every Statement
Suspension
- Sub-Clause 16.1 on the unamended forms
- Not less than 21 days' notice first
- Financing charges keep running
- Delay and Cost claimed through Clause 20
Termination
- Opens when a certified sum is unpaid 42 days after the due date
- Sub-Clause 16.2 in 1999, 16.2.1 in 2017
- Exercised by notice, with strict formalities
- Often amended or removed in GCC contracts
Questions Contractors Ask
Late payment interest, answered.
How is late payment interest calculated under FIDIC?
Under Sub-Clause 14.8 [Delayed Payment], the contractor earns financing charges on the unpaid amount from the date for payment under Sub-Clause 14.7 until the money arrives. The annual rate is the reference rate plus three percentage points, unless the contract states another rate, and the charges are compounded monthly. In practice that means applying one twelfth of the annual rate to the balance each month, adding the charge to the balance, and pro-rating any final part month. FIDIC does not fix a day-count convention, so state your method when you submit the figure.
What rate applies to FIDIC 14.8 financing charges?
The default margin is three percentage points in both editions, but the base rate differs. FIDIC 1999 uses the discount rate of the central bank in the country of the currency of payment and states no fallback if none exists. FIDIC 2017 uses the average bank short-term lending rate to prime borrowers for the currency of payment at the place for payment. Failing that, it uses the same rate in that currency's country, then the rate fixed by its law. Either default gives way to a rate stated in the contract: the Particular Conditions in the 1999 forms, or the Contract Data in 2017, so check those first.
Do I need to give notice to claim FIDIC financing charges?
No. The 1999 text entitles the contractor to financing charges without formal notice or certification, and the 2017 edition confirms that the Sub-Clause 20.2 claims procedure does not apply. That does not mean the money arrives on its own. Put a dated calculation into each Statement so the charges stay visible to the Engineer. If your contract uses FIDIC's 2022 reprint of the 2017 Red, Yellow or Silver Book, new Sub-Clause 21.4 deems a Dispute to have arisen where financing charges remain unpaid 28 days after the contractor requests them, referable to the DAAB without a Notice of Dissatisfaction.
Can a contractor suspend work for late payment under FIDIC?
On the unamended forms, yes. Sub-Clause 16.1 lets the contractor suspend work or reduce the rate of work after giving not less than 21 days' notice of a missed payment under Sub-Clause 14.7. The suspension does not prejudice the financing charges. If a certified amount is still unpaid 42 days after the time for payment, Sub-Clause 16.2 (16.2.1 in 2017) adds a right to terminate by notice. Both steps carry strict formalities, so have the notices reviewed before you serve them.
What if my contract amends or deletes Sub-Clause 14.8?
Then the amendment governs. GCC Particular Conditions often reduce the margin, set a fixed rate, cap the charges or delete the clause entirely. Where a rate is stated, enter it as a custom rate and the calculator applies it with the same monthly compounding. If the amendment also removes compounding, treat the result as an upper bound. Where the clause is deleted, any right to compensation for late payment depends on the governing law, which in some jurisdictions restricts charges that resemble interest. That question needs a legal view on your contract.
Related reading and tools
This calculator applies the arithmetic of FIDIC Sub-Clause 14.8 to the inputs you enter. It is general information, not legal advice, and no consultant-client relationship arises from its use. Entitlement depends on your executed contract, any amendment to the payment and suspension clauses, the facts, and the governing law. Take professional advice before relying on any figure or serving any notice.
Get Started
Certified is not paid. Paid late is not free.
One conversation is usually enough to see whether your payment administration is collecting what the contract allows, or quietly writing it off.
What is your notice situation right now?
Select one to help us match you with the right specialist.
