Your Client Is Deducting Late-Finish Penalties: What to Do Next

8 min read
Your Client Is Deducting Late-Finish Penalties: What to Do Next

When your client deducts liquidated damages, the late-finish penalty written into your contract, do not simply accept it. Check the sum, check whether the delay was really yours, and tell your client in writing that you dispute it. Act within days. Every week of silence makes the money harder to win back.

Key takeaways

  • A late-finish penalty deduction is a claim by your client, not a final decision. You can question it and often reduce it.
  • Check the dates, the daily rate, the cap and any handover first. Mistakes in the arithmetic are common and easy to prove.
  • Object in writing within days, and ask for the extra time you are owed for every delay your client caused.
  • The way out for the long term is a contracts team that sends the right letters on time, so penalties never land unanswered.
In this article (8 sections)
  1. 1. What a Late-Finish Penalty Deduction Really Is
  2. 2. Step One: Check the Deduction Is Right
  3. 3. Step Two: Ask Who Really Caused the Delay
  4. 4. Step Three: Put Your Objection in Writing This Week
  5. 5. Step Four: Ask for the Extra Time You Are Owed
  6. 6. What You Find and What to Do About It
  7. 7. How to Stop Penalties Landing on the Next Project
  8. 8. Frequently Asked Questions

What a Late-Finish Penalty Deduction Really Is

Most construction contracts set a fixed amount the contractor pays for each day or week it finishes late. The client does not have to prove its real loss. It simply takes the amount from your next payment, or from your retention money, or calls on your bank guarantee.

That makes the deduction feel final. It is not. It is the client's view of who caused the delay and how much it is worth. You are allowed to question both, and many deductions are wrong in at least one way.

The danger is what happens if you stay quiet. A deduction left unanswered month after month starts to look accepted. Later, when you finally argue about it at the final account, the client will ask why you never raised it. Your silence becomes their evidence.

Step One: Check the Deduction Is Right

Before you argue about who caused the delay, check the arithmetic. These mistakes are common and easy to prove:

  1. The completion date. Has it already been moved by an earlier change, extra work or an agreed extension? Penalties only run from the current date, not the original one.
  2. The daily or weekly rate. Is it the rate in your signed contract, or a figure from a draft or a different section?
  3. The cap. Most contracts limit the total penalty, often to a share of the contract price. Check the client has not gone past it.
  4. Handover of part of the work. If the client took over and used part of the project early, many contracts reduce the rate for the rest.
  5. The end date. Penalties stop when the work is complete or handed over, not when the paperwork is signed.
  6. The right steps. Many contracts say the client must give you written notice or make a formal claim before it can deduct. If it skipped that step, say so.

Use the free LD Exposure Estimator to work out what the penalty should be on your own dates. If your figure is lower than the client's, you already have your first point.

Step Two: Ask Who Really Caused the Delay

A late-finish penalty is only fair if the lateness was your fault. On most projects, at least part of it is not. Look back through the project for delays that came from the client side:

  • Drawings, design answers or approvals that arrived late
  • Site access, power or a working area handed over late
  • Changes and extra work the client asked for
  • Materials or equipment the client was meant to supply
  • Payments made late, which slowed your work
  • Instructions to stop or slow down

For each one, you need to show what happened, when, and how it pushed back the finish date. That is where good records decide everything. A guide on delay published by the Society of Construction Law recommends that records are kept up to date and that requests for extra time are made as close as possible to the delay. Our article on the records that win or lose a claim explains what to keep.

There is a stronger point too. In some cases, if the client caused delay and the contract gives no proper way to give you extra time for it, the client can lose the right to charge late-finish penalties at all. We explain this in our article on when the client causes the delay.

Step Three: Put Your Objection in Writing This Week

A phone call or a site meeting does not protect you. A letter does. Send it to the person your contract names for notices, in the way the contract says, and keep proof that it arrived. Keep it short and factual:

  • Say that you do not accept the deduction, and give its amount and date
  • List any mistakes in the arithmetic you found in step one
  • Name the delays your client caused, with dates
  • Say that you are asking for extra time to finish, and that details will follow
  • Ask for the money to be released, and keep all your rights open

Stay polite. You are probably still working for this client, and a calm, clear letter is more likely to be read than an angry one. Firm and factual is enough.

Step Four: Ask for the Extra Time You Are Owed

The real answer to a late-finish penalty is extra time to finish. If you are given more time, the completion date moves and the penalty for that period falls away.

Most contracts set a deadline to tell your client in writing that you want extra time, often counted from when you first knew about the delay. Our article on the 28-day rule that kills more claims explains why that deadline matters so much. If you have already missed it, do not give up. Talk to someone who can read your contract and the local law, because there may still be a way through.

Local law can help as well. In some Gulf countries, including the UAE and Qatar, the law lets a court reduce an agreed penalty if it is far above the client's real loss. It is not automatic, and it does not replace a proper request for extra time, but it is worth knowing.

What You Find and What to Do About It

What you findWhat it meansWhat to do
The rate, dates or cap are wrongThe deduction is too highWrite to the client with your corrected figure and ask for the difference back
The client caused some of the delayYou may be owed extra time, which cuts the penaltyAsk for extra time in writing, with dates and records
You missed the deadline to ask for extra timeYour position is weaker, but not always lostGet advice on the contract and local law before you write anything else
The delay really was yoursThe penalty may be fairCheck the sum and the cap, then plan the cash and finish as fast as you can
The client took the money without the right stepsThe deduction may not be valid yetPoint out the missing step and ask for the money to be released

How to Stop Penalties Landing on the Next Project

Late-finish penalties are one of the ways contractors slowly bleed money. One unanswered deduction looks survivable. Add extra work that was never paid for, letters sent late and a hard contract signed in a hurry, and one difficult project can finish a healthy company. It is the most preventable reason contractors fail, because the fix is simple and known.

The fix is a proper contracts team: people who read the contract before you sign, send the right letter on time every time, keep the records, and answer every deduction the week it happens. Large contractors have one. Most SME contractors do not, and they pay for it later.

At CALIM, we give SME contractors that team. Our liquidated damages defence service checks the deduction, builds your request for extra time and writes the letters that protect your money.

Frequently Asked Questions

Can my client deduct late-finish penalties from my payment?

Usually yes, if the contract allows it and the client follows the steps the contract sets out. Many contracts let the client take the penalty from monthly payments, retention money or a bank guarantee. But the client must use the correct completion date, the correct rate and stay within any cap. Some contracts also require a written notice or formal claim first. If any of those are missing, you can object in writing and ask for the money back.

What should I do first when a penalty is deducted?

Check the numbers before anything else. Confirm the current completion date, the daily or weekly rate in your signed contract, the cap and whether the client took over any part of the work early. Then write to your client within days saying you do not accept the deduction and why. Keep the letter short, factual and polite, send it the way the contract requires, and keep proof that it arrived.

Can I get the deducted money back later?

Often you can, if you are given extra time to finish or if the deduction was wrong. When the completion date moves, the penalty for that period should be repaid, usually through a later payment or the final account. Your chances are much better if you objected in writing at the time and asked for extra time before the deadline in your contract. Money is far harder to recover when the deduction was never challenged.

What if part of the delay was my fault?

That is common, and it does not mean you must accept the whole penalty. Separate the delays your client caused from the ones you caused, with dates and records for each. You may be owed extra time for the client's share, which cuts the penalty, even if some of it stays. Being honest about your own delays also makes your request for the rest more believable.

Is it worth getting expert help with a penalty deduction?

It is worth it when the sum is large, when the client caused part of the delay, or when you are unsure whether you missed a deadline. An expert can check the deduction, read the contract and local law, and build the request for extra time with your records. The earlier they are involved, the more options you keep. Many contractors only ask for help at the final account, when most of the options have gone.

A penalty you answer this week is a dispute; a penalty you ignore becomes a debt. If one has landed on your project, start with a Free Contract Audit: a senior specialist reviews your contract and tells you what to do next.

Note: This article is general information about late-finish penalty deductions in construction contracts, not legal advice, and any deduction should be assessed against your own contract and the law that applies to it.

CC

CALIM Contracts Desk

Contracts, Claims & Commercial Advisory

This article is general information about construction contract practice, not legal advice. Entitlement, notice requirements and time bars turn on the specific wording of your contract and the governing law, which vary between projects and jurisdictions. Obtain advice tailored to your contract before acting on anything set out here.

Get Started

Have a question our articles do not answer?

The fastest answer is usually a 30-minute call with one of our senior specialists.

What kind of dispute or exposure are you facing?

Select one to help us match you with the right specialist.