Contemporaneous records are documents made at the time of the events they record, such as site diaries, progress reports, programme updates, correspondence, photographs and labour returns. Tribunals weigh them above later recollection because they were written before anyone knew which facts would be disputed.
Key takeaways
- Tribunals weigh contemporaneous records over later recollection, because they were made before anyone knew which facts would be disputed.
- Under FIDIC 2017, Sub-Clause 20.2.3 requires records made at, or immediately after, the event; the fully detailed claim is due within 84 days (Sub-Clause 20.2.4).
- In Walter Lilly v Mackay, the court accepted costs backed by a contemporaneous system but was wary of undocumented, after-the-fact opinions.
- Build a record system around five habits: daily diaries, dated photographs, monthly programme updates, an event file per claim, and weekly reconciliation.
In this article (8 sections)
- 1. What Does 'Contemporaneous Records' Mean?
- 2. Contemporaneous Records: Meaning in Law
- 3. Contemporaneous vs Contemporary Records: Is There a Difference?
- 4. The Records That Decide Delay and Disruption Claims
- 5. What Tribunals Accept and What They Reject
- 6. Correspondence as Contemporaneous Evidence
- 7. How to Build a Record System on Site
- 8. Frequently Asked Questions
Memory gets rebuilt around the dispute. A diary entry written that evening does not. Most project teams still treat record keeping as administration to catch up on later, and thin records sit behind most of the reasons EOT claims get rejected - not because the delay was invented, but because the evidence of it was never created.
What Does 'Contemporaneous Records' Mean?
A contemporaneous record is a document created at, or very close to, the time of the event it describes. Its weight comes from three features:
- Made inside the event window.
- Made by someone with direct knowledge.
- Made for the job rather than for a claim.
A site diary completed that evening qualifies. A narrative assembled six months later from memory does not.
A frequently cited authority is Attorney General for the Falkland Islands v Gordon Forbes Construction, a 2003 case under the 1987 FIDIC Red Book. The judge described contemporary records as original or primary documents, or copies of them, produced or prepared at or about the time giving rise to a claim.
The court also held that witness statements prepared afterwards could not stand in for them. A statement written after the event is recollection. A record made while the work was happening is a contemporary record.
Contemporaneous Records: Meaning in Law
In most forums the question is weight rather than admissibility, and timing drives weight. In England and Wales, the Civil Evidence Act 1995 tells a court weighing hearsay to consider whether a statement was made contemporaneously and whether it was made for a particular purpose. A diary entry written on the day passes both tests; a chronology drafted for the claim fails the second.
The judicial reasoning is now explicit. In Gestmin v Credit Suisse in 2013, Leggatt J explained that memory is fluid and reshaped by litigation itself. His conclusion was that the best approach in a commercial trial is to place little if any reliance on recollections of meetings and conversations, and to base findings on the documentary evidence.
The claimant carries the burden of proof, and UAE evidence law states the same rule: the party making a claim must prove it. A tribunal cannot award what nobody can prove - a claim can be valid and unprovable.
Contemporaneous vs Contemporary Records: Is There a Difference?
In substance, no. FIDIC says contemporary records, English judges and the SCL Protocol usually say contemporaneous, and both mean records made at the time. The confusion comes from everyday English, where contemporary usually means modern.
Under Sub-Clause 20.1 of the 1999 FIDIC Red and Yellow Books, the contractor must keep such contemporary records as may be necessary to substantiate any claim, and the Engineer may monitor and inspect them. The 2017 suite sets a tighter window: Sub-Clause 20.2.3 defines them as records prepared or generated at the same time as, or immediately after, the event or circumstance giving rise to the claim. It adds that the Engineer's monitoring does not mean the records are accepted as accurate or complete.
Under Sub-Clause 20.2.4, the fully detailed claim is due within 84 days after the contractor became aware, or should have become aware, of the event, or within any other period the Engineer agrees. It must include all the contemporary records relied on, and if it lacks a statement of the contractual or legal basis by that deadline, the Notice of Claim lapses. The 28-day notice rule decides whether the claim survives. The records decide whether it can be proved and what it is worth.
The Records That Decide Delay and Disruption Claims
The SCL Delay and Disruption Protocol sorts project records into six categories: programme, progress, resource, costs, correspondence and administration, and contract and tender documents. On a delay or disruption claim, these records do most of the work, and each fails in a predictable way.
| Record | What it proves | The common failure |
|---|---|---|
| Daily site diary | Weather, labour, plant, work by location and instructions, day by day | Written up weekly or generically, so it cannot date an event |
| Progress reports | Progress against programme and causes of slippage seen at the time | Causes described differently from the later claim |
| Programme updates | How each event moved the critical path when it happened | No updates after the baseline |
| Correspondence and notice register | Notices served on time and instructions given | Letters filed but never indexed to an event or clause |
| Meeting minutes | What was raised, agreed and left open, and by whom | Issued late, never agreed, or silent on delay |
| Dated, located photographs | The state of the works on a given day | Undated images on personal phones |
| Inspection and test requests | When the Engineer was asked to attend and when it did | No log of request and attendance times |
| Labour and plant returns | Resources available, and resources idle during delay | Site-wide totals not allocated to activities |
| Cost records and timesheets | Actual time-related cost of the extended period | Allocated after the event, unlinked to the delay period |
| As-built programme | When work actually started and finished | Compiled at completion from fragments |
Resource records work twice, rebutting any allegation of under-resourcing and proving the prolongation cost of what stood idle. Sub-Clause 8.3 of the 1999 and 2017 Red Books requires a revised programme whenever the current one stops reflecting actual progress, and those revisions feed most delay analysis methods.
Disruption claims lean on records even harder. The Protocol calls the measured mile the most widely accepted way to prove lost productivity, where the necessary records exist. Without labour hours coded to activities, there is no mile to measure.
What Tribunals Accept and What They Reject
The SCL Delay and Disruption Protocol states the standard plainly: records relevant to progress and delay must be generated contemporaneously as the works progress, and not afterwards. It recommends that progress, resource and cost records state facts, not opinions, and be signed where practicable by both the contractor and the contract administrator.
The courts apply the same logic. In Walter Lilly v Mackay [2012] EWHC 1773 (TCC), Akenhead J accepted the contractor's recorded preliminaries costs as sufficiently accurate because they came from a contemporaneously maintained cost system, cross-checked on site. He also noted that without a contemporaneous critical path programme from February 2007, the delay experts could not readily run the monthly time-slice exercise they would probably have used.
A time-slice windows analysis depends on exactly those updates. What gets rejected is instructive too: the judge was wary of giving significant weight to the supposedly contemporaneous views of people who never gave evidence, where nobody could say what analysis lay behind them. A fact recorded at the time is strong. An opinion recorded at the time is only as strong as the person willing to defend it.
Nor did the court demand perfection. The judge accepted that daily, item-by-item allocation of shared site costs across three linked projects would have been artificial. Tribunals want records that are honest, proportionate and consistent - a contradiction inside your own file damages a claim faster than a gap does.
Correspondence as Contemporaneous Evidence
Contemporaneous correspondence is often the strongest evidence a contractor holds, because it shows what each party knew while the issue was live. The Protocol recommends that every communication be uniquely numbered, dated, given a descriptive subject and distributed as agreed, with important oral communications confirmed in writing.
Email is the weak point, because threads fragment and key messages sit in personal inboxes. The Protocol suggests sending material communications as numbered letters or filing key emails centrally. A WhatsApp message sent on the day also counts, provided it is preserved with its date and sender intact.
Correspondence can also create rights. Under Sub-Clause 3.3 of the 1999 Red Book, a contractor can confirm an oral instruction in writing within two working days. Unless the Engineer rejects or replaces it within two working days of that confirmation, it becomes a written instruction. The trap is treating a helpful email as a notice: notices usually need their own form and period, which the notice deadline calculator tracks.
How to Build a Record System on Site
The problem is rarely a lack of documents. It is the absence of a system that makes them findable, consistent and tied to events. The Protocol recommends agreeing at the outset which records are kept, who produces and checks them, how often, in what format and who stores them.
On site, that comes down to five habits:
- Set a daily diary standard and audit it weekly.
- Date, locate and caption every photograph.
- Update the programme monthly with actual progress, so the critical path is recorded before anyone argues about it.
- Open an event file on the day of awareness and index every new record to it.
- Reconcile each week's diaries, progress reports and payment applications - the same week told three ways is a gift to the other side.
Keep emails and programmes in native format, and retain everything until the defects period, any dispute and the limitation period have run.
A filing system that cannot produce every record for one event within minutes is a storage system, not an evidence system. We review hundreds of delay and disruption claims across the GCC every year, and the pattern is consistent: the entitlement existed on the day of the event, but the evidence to carry it was never created, and no drafting at submission can manufacture it.
At CALIM, we build a records matrix into every claims engagement, mapping each clause the claim relies on to the records that prove it while events are still live. Our EOT claims consultants start from that file, because a delay analysis is only as reliable as the records behind it.
Frequently Asked Questions
What does 'contemporaneous records' mean?
Contemporaneous records are documents created at, or immediately after, the time of the events they describe, in the normal running of the work rather than for a dispute. In construction they include site diaries, progress reports, programme updates, correspondence, dated photographs, labour returns and cost records. Their value comes from timing. Made before anyone knew which facts would be disputed, they are trusted over witness statements prepared later.
What is the meaning of contemporaneous records in law?
In law, a contemporaneous record is one made at or near the time of the matters it records, and that timing drives the weight it carries. The Civil Evidence Act 1995, which applies in England and Wales, lists contemporaneity as a factor when a court weighs hearsay evidence. English commercial judges also prefer documents to later recollection, because memory is reshaped by time and litigation. A claimant without contemporaneous records starts at a serious disadvantage.
What are contemporary records in construction?
Contemporary records is the term FIDIC uses for what lawyers usually call contemporaneous records. Sub-Clause 20.2.3 of the 2017 FIDIC suite defines them as records prepared or generated at the same time as, or immediately after, the event or circumstance giving rise to the claim. Clause 20.1 of the 1999 forms requires the contractor to keep the contemporary records needed to substantiate any claim. In both editions, contemporary means made at the time, not modern.
What is contemporaneous evidence?
Contemporaneous evidence is evidence created while the events in question were happening, rather than produced afterwards for a dispute. In a construction claim that means diaries, programme updates, photographs, correspondence and cost records from the project itself, not witness statements or retrospective chronologies. Tribunals still hear witnesses and experts, but they test that later evidence against the record. Where the two conflict, the record made at the time usually prevails.
Is contemporaneous correspondence good evidence in a construction claim?
Yes. Letters, emails, instructions and minutes sent while an issue was live show what each party knew at the time, which makes them highly persuasive. Emails and messaging app messages count if they are preserved with dates and senders intact. Correspondence is not automatically a contractual notice, however. Most contracts require notices in a specified form, to a specified address, within a specified period, so serve formal notices separately.
Claims are decided by what was written that evening, not what is remembered later.
Note: This article is general information on contemporaneous records in construction claims, not legal advice. Record-keeping duties and the weight of evidence depend on your contract, the governing law and the forum.
Tools and next steps for this topic
CALIM Contracts Desk
Contracts, Claims & Commercial Advisory
This article is general information about construction contract practice, not legal advice. Entitlement, notice requirements and time bars turn on the specific wording of your contract and the governing law, which vary between projects and jurisdictions. Obtain advice tailored to your contract before acting on anything set out here.

