When to Bring In a Delay Analysis Expert, and What to Send Them

6 min read
When to Bring In a Delay Analysis Expert, and What to Send Them

A delay analysis expert reconstructs who caused a project delay and whether it affected completion, using your programme and records. Bring one in as soon as a delay claim looks contested, not once it reaches arbitration, because the method chosen depends on records that must exist from day one.

Key takeaways

  • Bring in a delay analysis expert as soon as a delay claim is contested, not once it reaches adjudication or arbitration.
  • The method available depends on what records exist: a live programme supports a prospective method, gaps force a weaker retrospective one.
  • Send the baseline programme, every revision, progress updates and contemporaneous correspondence before the first call, not during it.
  • A delay analysis expert tests the critical path; a claims consultant runs the wider notice, quantum and submission.
In this article (7 sections)
  1. 1. What Does a Delay Analysis Expert Actually Do?
  2. 2. Five Signs You Need a Delay Analysis Expert Now
  3. 3. What to Send a Delay Analysis Expert Before the First Call
  4. 4. Which Delay Analysis Method They Will Likely Use
  5. 5. How Delay Analysis Experts Charge and What Drives the Fee
  6. 6. What a Delay Analysis Expert Cannot Fix for You
  7. 7. Frequently Asked Questions

What Does a Delay Analysis Expert Actually Do?

A delay analysis expert, sometimes called a forensic delay analyst, reconstructs the cause-and-effect chain between a delaying event and the project's completion date. The work is technical: building or reviewing the programme, testing which activities were critical, and applying a recognised method to show what actually drove the overrun.

That is different from a claims consultant's broader role, which covers notice, quantum and the written submission end to end. The wider claims team, and when each specialist is needed, is covered in claims consultant vs lawyer.

Five Signs You Need a Delay Analysis Expert Now

Most delay claims start without one. Bring in a delay analysis expert as soon as any of the following is true, because the records a method needs are the records you should already be keeping, not the ones you reconstruct after the fact.

Bring one in now if:

  • The employer or engineer disputes the critical path on your extension-of-time claim.
  • Two or more delay events overlap and you need to show which one actually drove the overrun.
  • The contract specifies a delay analysis method you have not used before.
  • The claim is heading to adjudication, a DAAB referral or arbitration.
  • Your own programme updates have gaps that a time-based argument alone cannot bridge.

What to Send a Delay Analysis Expert Before the First Call

A first call is only useful if the expert can see the record. Assemble it before the call rather than during it, because the choice of method depends on exactly what exists and how complete it is.

A useful starting pack includes:

  • The as-tendered baseline programme and every approved revision.
  • Monthly or weekly progress updates, with the critical path visible in each.
  • Delay event notices and the contemporaneous correspondence around them.
  • Site diaries, instructions, variation orders and as-built progress photographs.
  • The contract's own delay analysis clause, if the Particular Conditions name one.

Which Delay Analysis Method They Will Likely Use

The SCL Delay and Disruption Protocol groups methods by what they need and when they are run - prospectively, while the job is live, or retrospectively, once it has finished. An expert chooses the method the records actually support, not the one that tells the best story.

MethodWhen it is usedWhat it needs
As-planned vs as-builtRetrospective, simple claimsBaseline and as-built programme only
Windows / time sliceRetrospective, the SCL-preferred methodBaseline plus a full set of contemporaneous updates
Time impact analysisProspective, while the job is liveA live, well-maintained programme to insert the delay into
Collapsed as-builtRetrospective, no reliable baselineA detailed as-built programme and strong causation evidence
Impacted as-plannedProspective, fast but exposed to challengeOnly the original baseline programme

Each method is explained in full, with when it wins and when it is vulnerable to challenge, in our delay analysis methods overview.

How Delay Analysis Experts Charge and What Drives the Fee

Fees are usually time-based, not a percentage of the claim, and the main driver is the state of your records. A well-kept programme and contemporaneous diary is quick to analyse. A reconstructed history with gaps takes far longer, whatever method is eventually used.

Engaging a delay analysis expert early, while the programme is still live, is cheaper than engaging one after the fact, because most of the cost in a late instruction is spent rebuilding records that should already exist.

What a Delay Analysis Expert Cannot Fix for You

No method repairs a notice that was never served or a programme update that was never issued. The expert can work with imperfect records, but weak records narrow which methods are available and how confidently the result can be defended. Tracking notice deadlines as events happen protects the analysis before it is ever needed.

Frequently Asked Questions

What does a delay analysis expert do?

A delay analysis expert, also called a forensic delay analyst, examines a construction programme and its updates to establish whether a specific event delayed completion and by how much. The work involves identifying the critical path, testing competing causes of delay, and applying a recognised method such as windows analysis or time impact analysis to quantify the effect. The output is usually a report that supports, or tests, an extension-of-time claim. It is a technical and programming-led role, distinct from drafting the notice or negotiating the settlement, both of which typically sit with a claims consultant.

When should I bring in a delay analysis expert?

As soon as a delay event is disputed, or as soon as more than one delay event could be competing for the same period of critical delay. Waiting until a claim is formally rejected, or until the matter reaches adjudication or arbitration, narrows the available methods, because contemporaneous records that should have been created along the way may no longer exist or may not have been kept with the right detail. Bringing an expert in early, even just to review how records are being kept, is usually cheaper than reconstructing a programme history after the event.

What is the difference between a delay analysis expert and a claims consultant?

A delay analysis expert focuses narrowly on the programme: establishing the critical path and the cause-and-effect chain between an event and the completion date. A claims consultant runs the wider claim, including notice compliance, quantum and the written submission, and may instruct a delay analysis expert as part of that work. On a straightforward claim one person may do both jobs. On a large or contested claim, particularly one with several competing delay events, the two roles usually sit with different specialists working together.

What records does a delay analysis expert need from me?

At minimum, the as-tendered baseline programme, every approved revision to it, and the periodic progress updates that show the critical path over time. Beyond the programme, contemporaneous correspondence, delay event notices, site diaries, instructions and variation orders let the expert test cause and effect against what actually happened on site, not just what the programme predicted. The more complete and contemporaneous the record, the wider the choice of method and the more defensible the resulting analysis will be if it is challenged.

Which delay analysis method will a delay analysis expert use?

It depends on what the contract requires and what the records support, not on preference. A live, well-maintained programme favours a prospective method such as time impact analysis, run while the job continues. A finished project with full contemporaneous updates favours a retrospective windows or time-slice analysis. Where the baseline or the updates are incomplete, a collapsed as-built or impacted as-planned approach may be the only option available, each with known weaknesses the other side will test. The SCL Delay and Disruption Protocol sets out how these methods differ and when each is appropriate.

Send the records before you send the question, because the method is chosen by what exists, not by what you need it to prove.

Note: This article explains when and how to engage a delay analysis expert and is not legal or expert-witness advice; the right method and expert for your contract depend on its specific records, programme and governing law.

CC

CALIM Contracts Desk

Contracts, Claims & Commercial Advisory

This article is general information about construction contract practice, not legal advice. Entitlement, notice requirements and time bars turn on the specific wording of your contract and the governing law, which vary between projects and jurisdictions. Obtain advice tailored to your contract before acting on anything set out here.

Get Started

Have a question our articles do not answer?

The fastest answer is usually a 30-minute call with one of our senior specialists.

What do you need the delay analysis for?

Select one to help us match you with the right specialist.