Getting extra time to finish a delayed job protects you from late-finish penalties. It does not pay for the extra weeks you spent on site. That money is a separate request, with its own proof. Many contractors win the time, forget the money, and pay for the client's delay out of their own profit.
Key takeaways
- Extra time to finish stops late-finish penalties. It does not pay for the extra weeks you spend on site.
- The extra cost of being on site longer is a separate request, with its own proof: payroll, hire invoices, insurance and overhead records.
- The days of extra time you are given set the limit on the money you can claim for the delay.
- Start both on day one: a letter that asks for time and money, cost records split from the delay date, and a named owner for each.
In this article (6 sections)
Your contract and your consultant may call these an extension of time (EOT) and prolongation cost. Here we use plain words: extra time to finish, and the extra cost of being on site longer. They come from the same delay, but they are two different things, and each one has to be asked for and proven on its own.
Extra Time and Extra Money: What Is the Difference?
Extra time to finish moves your completion date. Its job is defensive. If the client caused the delay, you should not pay penalties for finishing late. Extra time stops money leaving your account. It does not bring any in.
The extra cost of being on site longer is the money side. Every extra week, you keep paying for site staff, cabins, equipment, insurance, bank guarantees and the head office that supports the job. If the client caused the delay, you should be able to recover those costs.
| Question | Extra time to finish | Extra cost of being on site longer |
|---|---|---|
| What it does | Moves the finish date | Pays for the extra weeks on site |
| What it protects | You from late-finish penalties | Your profit on the job |
| Who usually prepares it | The planning team | The commercial or cost team |
| Main proof | The programme and what caused the delay | Payroll, hire invoices, insurance and overhead records |
| If you skip it | You may pay penalties | You pay for the delay yourself |
| When to start | The day the delay starts | The same day |
A delay caused by the client can give you both. A delay nobody controls, such as extreme weather, often gives you time but no money. Your contract decides which events bring money as well as time, so check it early. The Society of Construction Law's Delay and Disruption Protocol, a widely used industry guide, also treats time and money as separate questions.
Why Contractors Win the Time but Lose the Money
The pattern is common. A delay hits. The planning team proves it and asks for more time. The consultant agrees. Everyone relaxes, because the threat of penalties has gone. The money side waits. By the time someone asks what the extra months cost, the records are patchy and the people who knew the details have moved to other jobs.
Three habits cause this:
- Penalties feel urgent, costs do not. A penalty is a deduction you can see on the next payment. The cost of staying longer builds quietly in your own accounts.
- Nobody owns the money side. Planners hold the programme, not the cost data. On a small team, the money request falls between desks.
- One letter feels like enough. Your first letter about the delay may protect both rights. You still have to follow it with a detailed money request, with figures and proof.
What Can You Claim for the Extra Time on Site?
You can usually claim the costs that run with time. These are costs that keep going for as long as you stay on site, whether or not much work is being done:
- Site staff: project manager, engineers, supervisors and safety officers.
- Site set-up: cabins, fencing, power, water and security.
- Equipment you had to keep on site, such as cranes and scaffolding.
- Insurance and bank guarantees that had to be extended.
- A fair share of head office costs, worked out with a recognised method.
- Financing costs, where your contract allows them.
Each cost must be real, and it must be caused by the delay. A monthly site rate multiplied by the months of delay is rarely accepted on its own. Expect your client to ask for payroll, hire agreements, insurance renewals and accounts.
Head office costs are usually the most argued item. Our guide to calculating the extra cost of being on site longer explains the accepted methods. The free Head Office Overhead Calculator gives you a first figure in minutes.
How the Extra Time Decides the Money
The days of extra time you are given set the window for the money. If you get 90 extra days because the client gave you the site late, you claim the costs of those 90 days. If the client shows that part of the delay was your own, and you get 60 days, the money claim shrinks to match.
So proving what caused the delay matters twice. It decides your time, and it caps your money. When a delay is large or disputed, our delay analysis support sets out clearly which days belong to the client, so both requests stand on the same proof.
Build Both Requests From Day One
The fix is simple, but it needs discipline. Treat every delay as two jobs running side by side from the first day:
- Write to your client as soon as the delay starts, and say you expect both extra time and the extra cost. Check the deadline in your contract to tell your client in writing - the free notice deadline calculator puts dates on it.
- Name one person for the time side and one for the money side.
- Split your site costs from the date the delay started, so the extra weeks can be seen apart from the normal job.
- Keep a written record of what happened on site each day: who was there, what equipment stood idle and what was held up.
- Send the detailed money request with the time request, or soon after. Do not leave it for the last payment settlement.
An extra week of a site team and cranes is real money for an SME. Over a few months it can be the whole profit on the job. Recovering it is not luck. It comes from letters and records done on time, every week, while the job is running.
That weekly work is what a contracts team does. Not having one is the most preventable reason contractors fail: rarely one disaster, more often a slow loss of money on job after job. CALIM gives SME contractors that team when they need it, without the cost of building one.
Frequently Asked Questions
What is the difference between getting extra time and getting paid for a delay?
Extra time to finish moves your completion date, so you do not pay late-finish penalties for a delay the client caused. Getting paid for the delay is a separate request. It recovers the extra cost of being on site longer: site staff, cabins, equipment, insurance, bank guarantees and a share of head office costs. Contracts often call these an extension of time and prolongation cost. Both come from the same delay, but each needs its own request and its own proof.
Can I claim the extra cost if I have not been given extra time?
It is possible, but much harder. Being given extra time is the clearest proof that the delay was the client's and how long it lasted. Without it, you must prove both of those things inside your money request, which gives the client more reasons to reject it. The better route is to ask for both from the start, in the same letter, and to keep pressing for a decision on the time so the money has a firm base.
What costs can I claim for staying on site longer?
Usually the costs that run with time: site staff salaries, site cabins and services, security, equipment you had to keep on site, extended insurance and bank guarantees, and a fair share of head office costs worked out with a recognised method. Financing costs may be included where your contract allows. Each cost must be real and caused by the delay, so keep payroll, hire agreements and invoices. Estimates and simple monthly rates are often challenged.
Why do contractors get the extra time but not the money?
Mostly because the money side starts too late. Penalties feel urgent, so the team rushes the time request. The cost request waits until after the time is agreed, by which point the records are patchy and the details forgotten. Often nobody owns the money side, because planners hold the programme but not the cost data. Naming an owner for each side on day one, and splitting cost records from the delay date, fixes most of this.
When should I start tracking the cost of a delay?
On the day the delay starts, the same day you write to your client about it. The records that prove your costs must be made as the money is spent, not rebuilt months later. Split your site costs from that date, keep a written record of what happened on site each day, and file payroll, equipment hire and insurance papers as you go. Records made at the time are much harder for a client to argue with.
Extra time without the money is only half of what you are owed.
If you have been given extra time but not the money, or a delay is building on a job now, start with a Free Contract Audit. A senior specialist reviews your contract and tells you what you can claim for the delay and what to send next.
Note: This article is general information, not legal advice. What you can claim for a delay, and the deadlines for asking, depend on your contract and the facts of your job, so get advice on your own position.
Tools and next steps for this topic
CALIM Contracts Desk
Contracts, Claims & Commercial Advisory
This article is general information about construction contract practice, not legal advice. Entitlement, notice requirements and time bars turn on the specific wording of your contract and the governing law, which vary between projects and jurisdictions. Obtain advice tailored to your contract before acting on anything set out here.

